Following on from the successful development at 182 Balham High Road, we were approached by another private developer to build out a similar scheme on the neighbouring site, consisting of five residential apartments over the ground floor and basement  commercial unit. 
This new build scheme was constructed in a similar fashion, with a lightweight steel frame structure and SFS wall infills clad with a brickslip cladding system. The existing basement was extended to the rear to incorporate the new intake room, bicycle and refuse stores. 
The contemporary fit out was carried out to a high specification with some unique finishing touches such as oak wall panelling from Wood Veneer Hub, and glazed green bricks to bath surrounds. 
Kitchens and worktops were supplied by Krieder. 

VALUE

£1.3m

COMPLETED

Oct 2022